| What | Who | When | Status |
| Project Initiation & Communication | Layla, Husham, Adrian | Feb 24th - Feb 28th | Ongoing |
| Set up Steering Committee & Working Group (dept/campus representatives) | Layla, Husham, Adrian | Feb 26th - Feb 28th | |
| Obtain licences, install Sharepoint 2007 and set up test site | Husham & I.T. Dept. | Feb 25th - Mar 4th | Ongoing |
| Review existing sharepoint, network drive and "intranet" usage | Adrian | Feb 22nd - Feb 28th | Ongoing |
| Consult with all staff regarding new intranet requirements | Adrian | Feb 18th - Mar 3rd | Ongoing |
| Dept/campus representatives to begin identifying & organising information & services to be added to the intranet | Dept/campus reps | Mar 1st - Mar 15th | |
| Create wireframe of new intranet structure & services | Adrian | Feb 26th - Mar 2nd | |
| Complete scope of current "intranet" activity & migration needs | Husham, Adrian, current intranet admins - e.g. Janet | Feb 27th - Mar 6th | |
Project Contacts
> Layla Al Bloushi. Deputy Director HR & Finance. Dubai Campus. Email: layla.albloushi@iat.ac.ae> Husham Zaki. Dubai Campus. Email: husham.zaki@iat.ac.ae
> Adrian Lobo. Dubai Campus (A217). Email: adrian.lobo@iat.ac.ae
No comments:
Post a Comment