Project Execution/Action Plan

What
Who
When
Status
Project Initiation & Communication
Layla, Husham, Adrian
Feb 24th - Feb 28th
Ongoing
Set up Steering Committee & Working Group (dept/campus representatives)
Layla, Husham, Adrian Feb 26th - Feb 28th

Obtain licences, install Sharepoint 2007 and set up test site
Husham & I.T. Dept.
Feb 25th - Mar 4th
Ongoing
Review existing sharepoint, network drive and "intranet" usage
Adrian
Feb 22nd - Feb 28th
Ongoing
Consult with all staff regarding new intranet requirements
Adrian
Feb 18th - Mar 3rd
Ongoing
Dept/campus representatives to begin identifying & organising information & services to be added to the intranet
Dept/campus reps
Mar 1st - Mar 15th

Create wireframe of new intranet structure & services
Adrian
Feb 26th - Mar 2nd

Complete scope of current "intranet" activity & migration needs
Husham, Adrian, current intranet admins - e.g. Janet
Feb 27th - Mar 6th






Project Contacts

> Layla Al Bloushi. Deputy Director HR & Finance. Dubai Campus. Email: layla.albloushi@iat.ac.ae
> Husham Zaki. Dubai Campus. Email: husham.zaki@iat.ac.ae
> Adrian Lobo. Dubai Campus (A217). Email: adrian.lobo@iat.ac.ae

No comments: